Pembangunan Flyover Tanjung Barat dan Lenteng Agung Sudah 60 Persen
.
photo Aldi Geri Lumban Tobing - Beritajakarta.id

Tanjung Barat and Lenteng Agung Flyovers Development Has Reached 60 Percent

The development progress of the Tanjung Barat and Lenteng Agung flyovers has now touched 60 percent. It has entered the upper structural development stage in the form of lifting the steel girder bridge.

Actually our target is in 2020, but it is impossible

"In line with that, the oprit flyover is also under construction in the form of sand and rock piles as a means for vehicles to get on the flyover," expressed Jakarta Bina Marga Agency Head, Hari Nugroho, Friday (6/5).

Due to COVID-19, its development is predicted to be complete in 2021.

City - Bekasi Inaugurates Cipendawa and Rawa Panjang Flyovers

"Actually our target is in 2020, but it is impossible," he told.

As for the information, the Lenteng Agung Flyover has 782 meters length and 6.5 meters width and Tanjung Barat Flyover has 1,052 meters length and 8 meters width.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye521 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye411 personBudhi Firmansyah Surapati
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye338 personDessy Suciati
  4. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye283 personAldi Geri Lumban Tobing
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye265 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik